4castplus Blog

4castplus Blog

26 26, 2017
Read More
31 31, 2016
Read More
04 4, 2015

EVM Explained: Planned Value

Many EV professionals would argue that Planned Value is one of the most important metrics in earned value analysis.  It provides the critical benchmark from which numerous other metrics are being compared.  

To give you an idea of what PV is, consider the example where you have a $1 million project that is scheduled to take 10 months to complete. An important aspect of project controls is to be able to plan out how that $1m will be spent over the 10 months. It obviously won’t be spent in one single lump. Neither will it be spent in an even, perfectly distributed rate over the 10 months.

The project spend will follow an uneven pattern – loosely following the schedule of activities and purchases that occur over the project’s duration. Planning the budget over the project’s timeline is called Time-Phased Budgeting. Planned Value is the value of scheduled project spend at a point in time of a project's duration.
Planned value is also referred to as Budgeted Cost of Work Scheduled (BCWS).

Read More
08 8, 2015
Read More
19 19, 2014

EVM Explained: Variance

“If you keep going at this speed, you’re going to be late!”

That’s my simplistic real-life analogy of earned value management. It’s a simple bit of math that we all do in our heads anytime we’re trying to get somewhere or finish something.  If you gave yourself an hour to get there and after a half-hour you’re still less than half-way, you’re going to be late.  It’s that simple. As simple as it is, it requires us to know quite a bit of information about the current situation in order to calculate late vs. on-time.  Just like EVM, you need to know 3 key elements to make the calculation:

Read More
23 23, 2014

I Have Mastered the Art of Talking to Myself Without Moving My Lips

Hey, don’t laugh, it’s a key skill. The only creepy thing about it is I can look at someone right in the eye and be muttering to myself at the same time. And even though I have at least another 40 years before I’m at that station in life where muttering is just something you do,  I’m getting an early start because I’ve discovered that it has high value.  I’m not the first to discover this, as it turns out. Experiments have been done to prove that regularly talking to yourself is a positive thing: http://newsfeed.time.com/2012/04/25/talking-to-yourself-may-actually-be-a-good-idea/.

Read More
05 5, 2013

How do you Figure out a Realistic Cost to Complete?

Project Owners spend an extraordinary amount of time trying to get an accurate reading on all the costs to complete for a project.  On big projects, it’s hard enough determining what’s been spent to date, nevermind remaining. Gathering the right information to calculate forecasted spend can be tricky to do and requires good tools & processes to piece together a realistic estimate of projected costs.

Read More
05 5, 2012

Why EVM Matters

Earned Value Management?

When asked about where their project stands against initial budget and schedule, most project managers will have a pretty good idea. They’d be able to tell you something like, “We’re running quite close to budget”, or “We’re almost half done”. However, without the tools and tracking to provide sufficient substance to those statements, gut-feel assertions like that are often dangerous guesses that can lead to cost overruns and delays. Earned Value Management provides the tools and techniques to tell a project manager where he or she really stands in their project. It can not only report on how much over/under budget or ahead/behind schedule a project is; it can also inform a PM as to how a project is trending, so as to better predict schedule and cost remaining to complete their project.  This provides the project manager a solid grounding on current status along with a good estimate of projected final results & timing.

Read More
05 5, 2012
Read More
02 2, 2012
Read More
1 2

Recent Posts

New Call-to-action